New Boundary Wall - Brunswick Way, Industrial Estate

We were commissioned by this busy North London Retail Estates Landlord to completely demolish over 80 metres of a 3 metre high delipidated and dangerously unstable boundary wall. Then to reconstruct, complete with new 2m deep reinforced concrete foundations, a 1m high reinforced concrete retaining wall.

This 13 week project which was completed in July 2016 and saw us create new brickwork comprising of over 40,000 mixed stock bricks in a similar pattern to the existing wall.

The project won high praise from all concerned due to the extremely high qulaity of the work, the minimal disruption to the Estates tenants and residentional neighbours and the timely manner in which the project was completed.

 